New Pool Progress

  • February 2021: Aquatics Master Plan Completed
  • February 2022: Ballot Measure 2A opened to public for comments on 8 Million dollar Bond for new pool
  • April 2022: Ballot Measure 2A passed
  • September 2022: Bond funds transferred to Town budget
  • November 2022:  RFPs out for Owners Representative
  • December 2022: 7 RFP responses for Owners Rep; 3 companies interviewed; Wember selected as Owners Representative
    • With a team of 6 people and over 100 years of pool construction experience they will: guide Town Staff in the decision making process, write all RFPs for the new pool project, manage all on site construction projects, manage the budget, and when construction is finished will complete a through walk through and create operational guidelines for the pool management team.
  • March 2023: RFPs submitted to the public for a General Contractor and Design Team
    • Submissions were due March 7
      • We received 4 submissions for design
      • We received 3 submissions for construction management
  • Upcoming:
    • Review RFP submissions and chose the General Contractor and Design Team
    • Parks and Recreation Commission form steering committee for capital campaign project
  • Goal New Pool Opening Summer 2024 unless design, construction, and/or supply chain problems occur.